Sunday, 24 December 2017

Week 24: Balcony Rail & Doors

Yep that was all thats done this week. :(

Looks like there was more done than just the balcony. Our doors and door frames were also installed.

It was delayed due to missing items which held back everything else. Glad it is sorted now.

Monday, 11 December 2017

Sunday, 3 December 2017

Week 22: Powder Room Tiling

Pretty slow week again.

This week only the powder room was tiled and the edges of the portico.

SS said doors should go on on Wednesday as he's finally able to source a new carpenter. Old carpenter has left to work for another company.

Hopefully will see more action this week.