Sunday, 19 November 2017

Week 20: Cornices Completed and Tiling Has Started

All cornices have been installed and tiling has started in wet areas.

The portico tiling is done, en-suite 2 and main bathroom tiling is nearly done but master en-suite is on hold until the shower hob is removed and that area re-waterproof. So main floor and downstairs wet areas tiling might start next week.

The two tiled bathrooms looks great and so glad that our selection turned out OK.

Cant wait to see the main floor tiled.

Saturday, 11 November 2017

Week 19: Kitchen, Vanity and Tiles Delivery

Kitchen were put in this week along with wet areas vanity. Looks great now that they are all in.

Next week looks like it will be tiles as they were delivered and also first coat of paint.

Doors and cornices still have not gone up yet, so guessing these will go on before painting start?


Saturday, 4 November 2017

Week 18: Waterproofing, Doors Delivered, Wall Sanded, Stairs Installed

So far this week we had waterproofing done, doors delivered and Electrical cutout done.

Ground floor sliding door has been put in also.

Walls were sanded on Friday and stairs have been installed.

Looks like it's locked up soon.